Introduction to The Residents Information Pack
5 Jun 2026

Dear Resident/Leaseholder,
Introduction
Bellway is committed to ensuring that buildings within the scope of the Government’s building safety programme are safe and meet current standards. Viceroy Court is being managed by Bellway’s Building Safety Division, which is responsible for identifying, planning, and delivering any remediation works required, at no cost to residents or leaseholders, where a building meets the relevant criteria.
This summary provides an overview of the work undertaken to date, what this has told us about the building, and the key factors influencing the next stages of the project.
Fire Safety Assessments Undertaken
During 2024,specialist fire safety surveys were completed at Viceroy Court including a Fire Risk Assessment of External Walls (FRAEW), undertaken in line with PAS 9980 guidance and a Fire Safety Assessment (FSA) undertaken in line with BS 9792 guidance.
The purpose of the FRAEW and the FSA are to assess the external wall construction of the building and the internal compartmentation and to determine whether the level of fire risk is considered tolerable or whether remediation is required to meet current standards. These assessments form part of the evidence required by Government and regulators before any remediation programme can be finalised.
In summary, the assessments confirmed that remediation works are required in order to bring parts of the development in line with current building safety expectations.
Based on the findings of the FRAEW and FSA and associated reviews, remediation works are required at Viceroy Court to address elements of the building’s internal compartmentation construction and ensure the development meets current building safety standards.
At a high level, the proposed works are expected to focus on:
1. addressing aspects of the internal compartmentation identified through the FRAEW and FSA process, and
implanting measures that reduce fire risk and improve overall building safety in line with current guidance.
The exact scope, design and sequencing of the remediation works will be developed in detail as part of the appointed Contractors next stages of the project and will be subject to regulatory approval.
Bellway recognises that any remediation activity can be disruptive and will ensure that, when works do proceed, appropriate measures are in place to manage safety, minimise inconvenience where possible, and keep residents informed throughout the process.
What Happens Next
Before remediation works can begin, a number of important regulatory and stakeholder steps must be completed.
Bellway must obtain a works access licence from its stakeholders before any remediation can begin. This licence is a requirement under the Self‑Remediation Terms (SRT). While these discussions are essential to securing the necessary agreements, they do introduce additional complexity to the planning process and may take time to conclude.
Programme and Timescales
At this stage, it is not possible to confirm an exact start date for remediation works at Viceroy Court. The need to obtain a works access license from its stakeholders, means that the programme remains subject to dependencies outside Bellway’s direct control.
Tenders to appoint a suitable contractor is already underway and we expect this to be completed in Q3 2026 and once appointed, further clarity on scope of works and timescales can be provided.
However, based on current progress and assumptions, Bellway is hopeful that works could commence in Q4 2026.This remains an indicative outlook only and will be kept under review as regulatory approvals and stakeholder agreements progress.
Keeping Residents Informed
Bellway recognises that uncertainty around timescales can be frustrating. The Building Safety Division remains committed to providing residents with clear and timely updates as key milestones are reached and as more certainty becomes available.
Further information will be shared once regulatory approvals are secured, and the scope and programme of works can be confirmed with confidence.
Kind regards,
Bellway’s Building Safety Team
Contact Details
In the first instance, if you have any questions relating to the remediation of your development, please contact your Managing Agent.
You can also contact Bellway using our dedicated Building Safety Helpline buildingsafety@bellway.co.uk